自学内容网 自学内容网

PMP--一模--解题--101-110

文章目录

11.风险管理–过程–识别风险→实施定性风险分析→实施定量风险分析→规划风险应对→实施风险应对→监督风险

101、 [单选] 在项目即将进入收尾阶段时,项目经理发现了一项原来没有考虑到的新风险。该风险一旦发生,可能给最终的可交付成果带来重要影响,甚至可能使其不能被客户接受。项目经理应该怎么做?

When the project is about to close, the project manager has identified a new risk that was not considered previously. Should this risk occur, it may cause a significant impact on the final deliverables, and may even make it unacceptable to the client. Then, what should the project manager do?

A:把该风险的影响通知管理层和客户
To inform the management and client of the impact of such risk

B:进行定性风险分析
To perform qualitative risk analysis

C:制定风险缓解措施
To work out risk mitigation action

D:增加应急储备
To increase emergency reserves

应急储备。在进度或成本基准内,为主动应对已知风险而分配的时间或资金。重点在于“已知风险”,排除D。选A。
在这里插入图片描述
在这里插入图片描述

14.敏捷–角色–产品负责人PO–职责–1.创建待办列表并排序;2.确认工作优先顺序;3.提供反馈;4.指导开发方向。–本次迭代已经结束,下次迭代是解决问题还是做新任务,需要PO给出优先级。

102、 [单选] 在敏捷迭代中,由于意外的挑战,任务1无法按时完成。项目中的另一个团队依赖于任务1的及时完成以完成他们的项目部分。项目经理应该如何解决这个问题?

During an agile iteration, Task 1 cannot be completed on time due to unexpected challenges. Another team within the project is depending on timely completion of Task 1 in order to fulfill their part of the project. How should the Project Manager resolve this issue?

A:分别与两个团队会面,让他们想出一个方法来满足要求的最后期限并按时完成项目
Meet with both teams separately and ask them to figure out a way to meet the required deadlines and complete the project on time

B:与产品负责人会面,重新确定迭代待办事项列表的优先级,以免影响其他团队或义务
Meet with the product owner to reprioritize the iteration backlog so that it does not impact other teams or obligations

C:增加项目团队的成员数量,并增加迭代长度,以确保工作将按照进度计划完成
Increase the number of team members for the project team and increase the iteration length ensuring that the work will be completed according to schedule

D:让团队成员知道你希望他们在困难条件下尽最大努力,并确保在经验教训中注意迭代的挑战
Let team members know you want them to do their best under difficult circumstances, and make sure to note the iteration’s challenges in lessons learned

B在这里插入图片描述

4.整合管理

103、 [单选] 一位新的项目经理最近在他们当前的组织中结束了一个项目。新项目经理使用了他们之前公司的最终项目报告格式,一位干系人评论说,虽然缺少了几条关键信息,但他们更喜欢这种格式。项目经理下一步应该做什么?

A new project manager recently ended a project in their current organization. The new project manager used the format of the final project report of their previous company, and a related party commented that although a few key pieces of information were missing, But they prefer this format.What should the project manager do next?

A:向其他项目经理提供报告的副本,并鼓励他们使用该报告
Provide copies of the report to other project managers and encourage them to use the report

B:使用批准的格式重新编写报告,然后与他们的经理讨论如何改进报告
Rewrite the report using an approved format and then discuss with their manager how to improve the report

C:考虑项目收尾完成的报告,并将该报告的副本存档
Consider a report on the completion of the project and archive a copy of the report

D:与项目团队开会,以审查项目报告格式并获得反馈意见
Meeting with the project team to review the project report format and get feedback

D
在这里插入图片描述

13.干系人管理–权力利益方格、权力影响方格、作用影响方格

104、 [单选] 在项目实施期间发生组织重组,一名关键干系人被替换。新的干系人对项目成功存在很高的兴趣并拥有足够的影响力,对项目结果产生重大影响。在执行干系人分析之后,项目经理该如何处理该新项目干系人?

Organizational restructuring occurred during a project’s implementation and a key stakeholder was replaced. The new stakeholder has high interest in the project’s success and enough influence and can significantly impact its outcome. After performing a stakeholder analysis, how should the project manager handle this new stakeholder?

A:监测干系人期望发生的任何变化。
Monitor any change in stakeholder in stakeholder expectation.

B:保持向干系人通知项目进度/状态。
Keep the stakeholder informed of the project’s progress/status.

C:确保干系人满意项目进度/状态。
Ensure stakeholder id satisfied with the project’s progress/status.

D:密切管理干系人的期望。
Manage the stakeholder’s expectation closely.

C 在这里插入图片描述
在这里插入图片描述

14.敏捷–预测

105、 [单选] 你正在领导一个开发新智能手机的项目。因为你要预测需求的许多变更,并不断从干系人那里得到反馈来调整智能手机,所以工作将以小的增量迭代完成。然而,这款智能手机的摄像头将由一家拒绝以渐进方式合作的供应商开发。你为该项目选择什么项目管理方法是最好的?

You are leading a project to develop a new smartphone. Since you are anticipating many changes in requirements and continuous feedback from stakeholders to adjust the smartphone accordingly, the work will be done iteratively in small increments. However, the camera for the smartphone will be developed by a vendor who refuses to collaborate in an incremental way. What project management approach is best for you to select for this project?

A:以敏捷方法为主,带有一些预测组件
Predominantly agile with some predictive components

B:以预测方法为主,带有一些敏捷组件
Predominantly predictive with some agile components

C:在计划过程中具有预测性,在执行过程中具有敏捷性
Predictive during planning and agile during execution

D:在计划和执行期间均以敏捷方法为主
Agile during planning and predictive during execution

在这里插入图片描述

11.风险管理

106、 [单选] 项目经理在产品开发的第三次迭代中意识到,用于项目管理计划的模板没有显示更新。项目经理应该采取什么行动?

A Project Manager realizes during the third iteration of product development that the template used for the project management plan is not showing updates. Which action should the project manager take?

A:指派一名团队成员更新项目管理计划模板并记录任何风险
Assign one team member to update the project management plan template and document any risk

B:根据即将到来的迭代的商业价值而对更新模板的需求进行排序
Rank the need to update the template according to the business value for the upcoming iterations

C:避免通过独立修复问题而使团队分心
Avoid adding to team distraction by fixing the issue independently

D:将问题记录为新的项目风险并提出解决方案
Document the issue as a new project risk and propose a solution

D在这里插入图片描述

14.敏捷

107、 [单选] 一家沉浸于传统瀑布式项目管理中的PMO聘请了你,作为敏捷实践者,来指导组织向敏捷的转变。在完成对组织文化的初步评估之后,你已经意识到许多干系人都抵制变更。你的最佳行动方案是什么?

A PMO steeped in traditional waterfall project management has hired you, as an agile practitioner, to guide the organization’s transformation to agile. After completing an initial assessment of the organizational culture, you have realized that many of the stakeholders are resistant to the change. What is your best course of action?

A:提供培训来确保员工更加专业化
Provide training to ensure the employees are more highly specialized

B:同时将所有项目向敏捷过渡
Transition all projects to agile at the same time

C:寻求愿意支持这一事业的高层高管
Seek a high-level executive willing to champion the cause

D:确保工作分解成孤岛
Ensure the work is decomposed into silos

C在这里插入图片描述

14.敏捷–方法–回顾–回顾是最重要的一个实践,原因是它能让团队学习、改进和调整其过程。

108、 [单选] 作为向敏捷转变的一部分,一个组织为一个项目选择一个试点团队来开发一个软件工具。一位敏捷教练被分配到团队中,在整个过渡过程中指导他们。在最初的几次迭代中,教练与项目经理和团队一起指导他们进行敏捷实践,并将任务分配给团队成员。敏捷教练采用什么最佳行动方案来确定团队是否获得了在没有教练的情况下执行即将到来的迭代所需的技能?

As part of its transformation to agile, an organization selects a pilot team for a project to develop a software tool. An agile coach is assigned to the team to guide them throughout their transition. For the first few iterations, the coach works with the project manager and team to coach them on agile practices and assign tasks to the team members. What is agile coach’s best course of action to determine if the team has acquired the required skills to perform the upcoming iterations without coaching?

A:参加每日站会 Attend daily standup meetings

B:进行产品演示 Conduct product demonstrations

C:举行迭代回顾 Hold iteration retrospectives

D:开展团队建设活动 Carry out team building activities

Scrum(敏捷型)
流程:
(1)迭代计划会(选故事、领任务、拆任务):输入产品Backlog 、冲刺目标 → 输出冲刺Backlog 、燃尽图、任务板
(2)每日站会(15分钟、轮流开、不解决问题):输入任务板/看板 →输出任务板更新、燃尽图更新、障碍日志、产品增量
(3)迭代评审会(演示、评审、反馈):输入产品增量 → 输出确认的产品增量、干系人的反馈
(4)迭代回顾会(总结、改进、计划):输入问题日志、干系人的反馈 → 输出改进计划、新的待办事项,选C。
在这里插入图片描述

9.资源管理

109、 [单选] 项目经理接管一个执行阶段的项目,在对项目进度进行初步审查期间,项目经理注意到与特定关键路径活动有关的信息不完整,有些活动还存在风险。项目经理如何才能确定每项活动的责任?

A project manager takes over a project in the execution phase,during an initial review of the progress, the project manager notices that information relevant to specific critical path activities is incomplete, and some activities are at risk. How could the project manager identify accountability for each activity?

A:工作分解结构 Work breakdown structure

B:责任分配矩阵 Responsibility assignment

C:组织分解结构 Organizational breakdown structure

D:风险登记册 Risk register

每项活动的责任,选择B。在这里插入图片描述

14.敏捷–项目生命周期–特征–敏捷是持续参与;预测是在特定里程碑参与;混合型建议定期参与。

110、 [单选] 你将与你的团队会面来确定项目的生命周期。在分析了定义和管理需求、开发可交付成果、处理变更、控制风险和成本,以及与关键干系人合作的最佳方式之后,做出了选择混合生命周期的决定。在选定项目生命周期后,关键干系人多久参与一次?

You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle changes, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle. With the project life cycle selected, how often will the key stakeholders be involved?

A:持续参与 Continuously

B:在特定里程碑参与 At specific milestones

C:定期参与 Regularly

D:完全不参与 Not involved at all

A 在这里插入图片描述
在这里插入图片描述


原文地址:https://blog.csdn.net/stqer/article/details/142138080

免责声明:本站文章内容转载自网络资源,如本站内容侵犯了原著者的合法权益,可联系本站删除。更多内容请关注自学内容网(zxcms.com)!